Hardware Status & Schedule
All SVT boards (8 different kinds) are now fully specified.
- Few small details will be adjusted as implementation allows
- None is waiting external input, boards design rolls to completion by end of year
Pre-production prototypes have started arriving.
- Will have one of each board by March.
- XTRP fanout will come later (not a problem)
Production will start in June, installation completed by end of year
3 month window in March-June to assemble 1/12th of SVT and test full operations before production start
- vertical (phi) slice test
- not just a test: a step in a continuos process to build full SVT hardware and software and integrate it in the Trigger/DAQ